Parking lot poured
Posted in Uncategorized
New sign installation
Posted in Uncategorized
Sidewalks have arrived
Sidewalks are being poured this week. They started pouring mid-day. They started with the sidewalks around the courtyard. They should all be complete by the end of this week.
Posted in Uncategorized
Frame signed off
We now have signoff from the city on all the framing for all the buildings. The insulation and sheetrock is complete in the classroom buildings and has now started in all the other buildings! The progress will go quite quickly now as the interiors begin to take shape.
We can finish the board and batten all around the outside where we have that on the exterior. The prep for stucco comes later in the process.
Posted in Uncategorized
Classrooms – Tyvek & Insulation
The classroom building is getting closed in, ready for the siding. The cedar soffit has been installed all the way around and the Tyvek is being applied. We received the frame certificate from the city, so we can close in this building.
The elecrical, plumbing, HVAC and sprinkler systems have all been installed.
The insulation is going in today and next week the sheetrock will be installed.